From the Health & Safety Day held in 2001, a number of questions were raised,
the answers to which are below. The HSE appreciates that these may not be
complete in all cases and in certain circumstances may need to be addressed on
an individual basis either by your Local Health & Safety Officer of the HSE. You
can forward your individual concerns via the PMMDA - see Contact Us Page.
Question 1
Schedule 4 to the Supply of Machinery (Safety) Regulations (SM(R)R) includes
injection and compression moulding machines with manual loading or unloading.
Manual loading can be equated to manual feeding. In the context of these
machines does this refer to loading polymer and unloading product?
Answer
Yes. However note that even where polymer is loaded into a hopper by hand,
this may not be considered "manual loading" of the machine i.e. where loading
from the hopper into the machine is automatic and there is no risk if the
machine starts up. However in this case the machine is still a schedule 4
machine if it is unloaded manually.
Back to Top
Question 2
Following on from the above, if the machine is loaded automatically and a
robot arm unloads the product, does this mean it is not a Schedule 4 machine?
Answer
Correct. Provided the above comprises the total machine i.e. no provision for
manual feed without changing the machine. As a general rule if the machine can
easily revert to use manually with minimum effort, HSE's view it that it remains
a Schedule 4 machine.
It is common in the industry to add vacuum hopper loaders to injection
moulding machines and/or pick and place robots to remove finished product. This
is encouraged to reduce manual handling risk. It can take place either at the
time of purchase of the injection moulding machine (IMM) or at some point during
its life. In answering the questions below both these circumstances have been
considered
Back to Top
Question 3
In adding this equipment/machinery to a Schedule 4 machine, what are the
implications for the supplier/user and do they turn to the approved body (who
maybe in another country) at any point? IMM's may or may not be built in
accordance with BS EN201.
Answer
The loader and robot may be specifically designed for this type of injection
moulding or similar machine, or may be a general design with no specific
application, In the latter case, they are not machines and so cannot be issued
with a Declaration of Incorporation. The former can.
If the IMM is not modified in any substantial way (e.g. removal of protection
devices/guards: interface with electronics etc) and could still be used manually
with minimum effort, it is considered the machine remains a Schedule 4 machine.
However, the whole complex machine is subject to SM(S)R and needs CE marking
etc. The Essential Health and Safety Requirments (EHSRs) of the individual
machines need not be re-assessed provided modifications have not affected that
area, e.g. if the control circuit or guarding of drives have not been modified
the original CE procedure for that machine is sufficient. Schedule 4
requirements do not have to be complied with provided this assembly of machines
results in automatic feed and unload. If it doesn't then the whole will need to
go through the Schedule 4 procedures and the responsible person (who will be
determined by reference to the definition of responsible person in each case)
has a choice of Approved Body. They do not need to go to the Approved Body who
dealt with the IMM - although there may be a cost advantage as they will have
all the etc.
NOTE: if the robot and feeds have not been CE marked (because they are
general machines with no specific application) the EHSRs relevant to there
operation will need to be addressed by the responsible person, which may be the
user, if they are putting the assembly of machines together. Where the hopper
loader and robot have a particular application they will/should be CE marked.
Back to Top
Question 4
Should a Declaration of Incorporation or Conformity be given for the hopper
loader or robot?
Answer
See above - it depends on whether it has been manufactured for specific or
general applications. If it is a machine and is sold to operate with the IMM
(i.e. will not be used independently) then a Declaration of Incorporation should
be issued. If it has no specific application or is not complete i.e.does not
have all the actuators, control and power circuits) it is not a machine and so
cannot be CE marked or issued with a Declaration of Incorporation.
Back to Top
Question 5
Who should be appointed to take on the role of dealing with a modified
machine?
Answer
The responsible person has ultimate responsibility. They should ensure a
competent person e.g. a suitable engineer - either from inside or outside the
company ensures that EHSRs are complied with. Where a Schedule 4 machine is
involved an Approved Body does not need to be involved unless significant
modifications are to be made to the IMM and it can still operate in manual mode.
Back to Top
Question 6
It is correct that unlike Section 6 of the Health & Safety at Work Act, the
Supply of Machinery (Safety) Regulations don't accommodation requires for
safeguards to be left off if a user request supply of a machine without them?
Answer
Yes, the exception ebing that if the supplied unit is a machine (see
definition) but the user does not want all the guards and other safety devices
fitted as they intend to combine it with other equipment/machines, they could
ask for a Declaration of Incorporation from the supplier (i.e. no CE mark) and
use the information from the supplier on how it meets the relevant EHSRs as part
of their Declaration of Conformity for the whole unit.
Essential Health & Safety Requirement 1.6.2 requires there to be access to
operating position and servicing points.
Back to Top
Question 7
What is the responsibility on the UK based supplier where an IMM is supplied
into the UK and it has a hopper feed which is not accessible from the floor and
yet safe means of access hasn't been supplied?
Is it any different for a granulator where no access is provided to the feed
opening?
Answer
In both cases access should have been supplied, the nature will depend on the
frequency and mode of access e.g. for infrequent access a ladder may suffice but
for routine access, especially if carrying materials, stairs would be needed
with hand rail etc.
Responsibility for failure to comply with the EHSRs will depend on the
particular circumstances. If the UK supplier is not the responsible person (i.e.
first supply, or manufacture is elsewhere in the EU/EEA) then the responsibility
on the UK supplier is to supply safe equipment and on the user to ensure the
EHSRs have been complied with. In both cases it may be possible to argue that
the defect was not apparent to the user or supplier (e.g. electrical control
circuit was faulty), but in this case they should have known the access
arrangements were unsafe (if there were no/poor means of access0. the breaches
are under SM(S)R Regulations 11(2) (supplier who is not the responsible person)
and the Provision and Use of Work Equipment Regulations 10(1) (user).
So the duty on the supplier is to ensure the equipment is safe, i.e. has
proper access. However, the responsible person (i.e. manufacturer/first supplier
in EU) has primary duty to meet the EHSRs under SM(S)R. However this cannot be
used as an excuse to use unsafe machines. In practice HSE will ask the
responsible person to correct the machine and similar machines in the EU and
circulate this information to other member states. If it is a blatant breach,
HSE may take enforcement action. HSE may also take action on the supplier in the
UK if fault should have been seen (as in this case). if it is a significant risk
HSE may also issue a Notice on the user to prevent use until the fault is
corrected.
Back to Top
Question 8
What are the duties on a conveyor supplier when they supply a conveyor at the
same time as the supply of a granulator which may be from another supplier or
imported directly by the user?
Answer
This depends on the integration of the two machines and intention of the
manufacturer.
If the two have been supplied independently and neither need major
modification in order to work together, neither supplier has additional duties
other than those they should have already complied with under SM(S)R for the
individual item of machines. Declarations of Conformity for both should be
issued.
However, a Declaration of Incorporation should be issued where the
manufacturer builds the machine with the intention that it is incorporated into,
or assembled with, a larger machine, i.e. cannot function as intended
independently of the larger assembly. In other words, to fulfill its intended
function, the machine needs to be incorporated into another relevant machines.
Irrespective of which Declaration procedure the machines comes under, the
relevant EHSRs have to be met.
In the case of a small conveyor for incorporation into a larger assembly, it
may not initially require guards for the head and tail drums, but electrical
hazards should be addressed by the conveyor manufacturer and appropriate
precautions taken to reduce such risks.
Back to Top
Question 9
What are the duties on the conveyor supplier when supply is after the
original supply of the granulator?
Answer
This will depend on the "agreement" but we would expect the supplier to
enquire as to use and give advice. With respect to other legal provisions, the
situation has not changed, e.g. it will be the user if they fit the machines
together etc, who will take on the role of ensuring the EHSRs are met and
issuing a Declaration of Conformity for the whole machine. They need to only
address those EHSRs that have not been adequately covered in any CE Declaration
of Conformity or Incorporation issued by the individual machine manufacturer.
Back to Top
GO TO :
2002 SPRING
SEMINAR QUESTION
HSE DEFINITIONS
H&S HOME